Priority #

Title

Jira Epic

Importance

Notes

Status

1

Label Printing

 

Must have at go live

Application SpineOMatic being tested (Ex Libris’s recommended software for spine labels).

Met with Desktop Support to share installation instructions and create timeline for application to be pushed to staff computers. RL and RD staff working on call number parsing and label testing.

KHN

2

Printing Hold Slips on Schedule

 

Must have at go live

Configuration - VMs, print daemon (desktop support not developers)

Met with Desktop Support to share installation instructions and create timeline for print daemon to be pushed to staff computers.

KHN

3

Standing up Leganto and integration with Canvas

 

Must have at go live

Configuration LTI with DLI; exporting Courses data

Loaded FOLIO courses, reading lists. LTI communication with Canvas working. Starting onboarding subject matter experts, working on loading .pdf files of readings.

KHN

4

Resource Sharing/ReShare

 

Must have at go live

May not require developers - Index Data will help with testing and set-up

5

ABLE Binding Software

Shortly after go-live

Uses z39.50 to communicate with Alma

Working Areas:

DulDev list of Alma integrations (DulDev Atlassian account required)

...