Priority # | Title | Jira Epic | Importance | Notes | Status |
---|---|---|---|---|---|
1 | Must have before go live |
| Full file runs Saturdays, incremental running daily. There’s a few more Jira issues to complete this integration. KHN | ||
2 | Must have at go live |
| Instance of TRLN Discovery is running locally, extracts from Alma can be done. Work ongoing on putting all the pieces together so testers can view Alma data in TRLN Discovery. | ||
3 | Must have at go live |
| Data mapping is complete, file can be sent to Accounts Payable. Early May, AP will review our file. Work is ongoing on reporting and Alma to AP data flow. KHN | ||
4 | Must have at go live | Can use code from Harvard as a start | Meeting planned with Harvard staff involved with this integration to share helpful tips KHN | ||
5 | Must have at go live |
| Patron information, loans, fees and fines information is available. Work is ongoing on viewing an item list and requests. KHN | ||
6 |
| Must have at go live |
| First meeting scheduled with CaiaSoft staff 5/2/2024. | |
7 | Must have at go live | Plan Discovery Working Group taking responsibility | |||
8 |
| Must have at go live |
| ||
9 |
| Must have at go live | or at least by early August | ||
10 |
| Must have at go live | tied to TRLN Discovery project | ||
11 |
| Post go live | Users will be able to view these logs in Aleph after go-live, but we need to import the data so that’s is available in Alma. | ||
12 |
| Post go live | Would need to adjust the landing page if not at go live | ||
13 | Migrate FOLIO ERM Organizations Contacts and Interfaces to Alma |
| Post go live | May not require developer resources, maybe Postman | |
14 |
| Post go live | Connection to DSC for item history | ||
15 |
| Post go live | Coding mostly done, working on some tweaks based on data review |
...