    • RA IT/Data WG
  • Data – Bib/Hol/Item Loaded
    • Data WG/LSIS
  • Permissions – Roles for ERM and permission sets
    • ERM IT/Permissions WG
  • Reporting – Prioritize reports for go-liveComplete ARC replacement search and write report
    • Reporting WG
  • Reporting – Gap analysis local reports needed vs. reports FOLIO offersContinue building reporting inventory with ITs
    • Reporting WG/ERM IT, RA IT, MM IT, RM  IT

...

  • ERM training completed
    • ERM IT/Doc+Training WG
  • Permissions – ERM staff assigned permissions
    • ERM IT/Permissions WG
  • FOLIO production instance in use for ERM
    • ERM IT
  • Data - Users Loaded
    • Data WG/LSIS
  • Data - Organizations (Vendors) Data Analysis/Mapping
    • ERM IT/Data WG
  • Configuration - Organizations, Acquisitions Units
    • RM IT/Configuration WG
  • Permissions – Roles for MM and permission sets
    • MM IT/Permissions WG
  • Reporting – Report on ARC replacement submitted
    • Reporting WG
  • Reporting – Continue building reporting inventory with MMIT, prioritize reports for go-live
    • Reporting WG/MM IT


August 2020

  • Workflows - 80% of functional requirements documented
    • ERM IT, RA IT, MM IT, RM IT/Workflows WG
  • Configuration - Finances, Invoices, Orders
    • RM IT, Configuration
  • Data – Loans, Fees/Fines Data Analysis/Mapping
    • RA IT, Data WG
  • Data – Organizations (Vendors) Data Loaded
    • Data WG/LSIS
  • Gap Analysis – Requirements in Duke Jira vs. Goldenrod
    • LSIS/All project teams
  • Permissions – MM staff assigned permissions
    • MM IT/Permission WG
  • Reporting – Generate reports resulting from gap analysisPhase 1: Gap analysis local reports needed vs. reports FOLIO offers
    • Reporting WG
  • Reporting – Deploy ARC replacement
    • Reporting WG
  • Retrospective - ERM Implementation

...

  • LDP staff interface launched
  • Data – Finances (Budgets) Data Analysis/Mapping
    • RM IT/Data WG
  • Data – Loans, Fines/Fees Loaded
    • Data WG/LSIS
  • Permissions – Roles for RA and permission sets
    • RA IT/Permissions WG
  • Reporting – Begin deploying required Select Phase 1 report team, train team, and begin deploying Phase 1 reports
    • Reporting WG/Phase 1 stakeholders (RAIT?)


October 2020

  • Configuration - Service Points, 
    • RA/Configuration WG
  • Data – Orders/Invoices Data Analysis/Mapping
    • RM IT/Data WG
  • Data – Finances Loaded
    • Data WG/LSIS
  • Gap Analysis – Requirements in Duke Jira vs. Honeysuckle
    • LSIS/All project teams
  • Permissions – RA staff assigned permissions
    • RA IT/Permissions WG

...

  • RA integrations complete
  • Reporting – Custom tables creation completed, all reports loaded into ARC replacement
  • RA Circulation Rules 50% complete
    • RA IT/Configuration WG

...

  • Permission sets for all roles
  • Reporting – Generate reports resulting from gap analysis completedReporting – Deployment of required FOLIO queries on ARC replacmenttraining and end user testing begins


April 2021

  • Decision Checkpoint #2
  • Testing scenarios written in Xray
  • Gap Analysis – Requirements in Duke Jira vs. Juniper
  • RA Circulation Rules complete
    • RA IT/Configuration WG

...

  • Final training
  • Go Live!


August 2021

  • Bug FixingReporting – Deploy ARC Replacement
  • Project Review


September 2021

...