These project milestones need to be completed by the end of the month in which they’re listed in order for Duke to be on schedule to implement FOLIO by the end of July 2021.

The Implementation Teams have final responsibility to make sure the work is done and these dates are met. The Working Groups are responsible for supporting driving the timelines and work with the Implementation Teams in getting teams to complete the work done.


May 2020

  • MVP gap analysis
    • LSIS/All project teams
  • Data – Item Data Analysis (Bib and Hol were done before May 2020)
    • MM IT/Data WG

...