These project milestones need to be completed by the end of the month in which they’re listed in order for Duke to be on schedule to implement FOLIO by the end of July 2021 .

The Implementation Teams have final responsibility to make sure the work is done and these dates are met. The Working Groups are responsible for supporting the Implementation Teams in getting the work done.


May 2020

  • MVP gap analysis
    • LSIS/All project teams
  • Data – Item Data Analysis (Bib and Hol were done before May 2020)

      ...

        • MM IT/Data WG


      June 2020

      • FOLIO production instance installed
        • LSIS/IndexData
      • Integration with Identity Management/SSO
        • LSIS/IndexData
      • Data – Users Data Analysis/Mapping
        • RA IT/Data WG
      • Data – Bib/Hol/Item Loaded
        • Data WG/LSIS
      • Permissions – Roles for ERM and permission sets
        • ERM IT/Permissions WG
      • Reporting – Prioritize reports for go-live
        • Reporting WG
      • Reporting – Gap analysis local reports needed vs. reports FOLIO offers

          ...

            • Reporting WG/ERM IT, RA IT, MM IT, RM  IT


          July 2020

          • ERM training completed
            • ERM IT/Doc+Training WG
          • Permissions – ERM staff assigned permissions
            • ERM IT/Permissions WG
          • FOLIO production instance in use for ERM
            • ERM IT
          • Data - Users Loaded
            • Data WG/LSIS
          • Data - Organizations (Vendors) Data Analysis/Mapping
            • ERM IT/Data WG
          • Permissions – Roles for MM and permission sets
            • MM IT/Permissions WG
          • Reporting – Report on ARC replacement submitted

              ...

                • Reporting WG


              August 2020

              • Workflows - 80% of functional requirements documented
                • ERM IT, RA IT, MM IT, RM IT/Workflows WG
              • Data – Loans, Fees/Fines Data Analysis/Mapping
                • RA IT, Data WG
              • Data – Organizations (Vendors) Data Loaded
                • Data WG/LSIS
              • Gap Analysis – Requirements in Duke Jira vs. Goldenrod
                • LSIS/All project teams
              • Permissions – MM staff assigned permissions
                • MM IT/Permission WG
              • Reporting – Generate reports resulting from gap analysis
                • Reporting WG
              • Reporting – Deploy ARC replacement

                   

                  ...

                    • Reporting WG


                  September 2020

                  • LDP staff interface launched
                  • Data – Finances (Budgets) Data Analysis/Mapping
                    • RM IT/Data WG
                  • Data – Loans, Fines/Fees Loaded
                    • Data WG/LSIS
                  • Permissions – Roles for RA and permission sets
                    • RA IT/Permissions WG
                  • Reporting – Begin deploying required reports

                      ...

                        • Reporting WG


                      October 2020

                      • Data – Orders/Invoices Data Analysis/Mapping
                        • RM IT/Data WG
                      • Data – Finances Loaded
                        • Data WG/LSIS
                      • Gap Analysis – Requirements in Duke Jira vs. Honeysuckle
                        • LSIS/All project teams
                      • Permissions – RA staff assigned permissions

                           

                          ...

                            • RA IT/Permissions WG


                          November 2020

                          • Data – Requests Data Analysis/Mapping
                            • RA IT/Data WG
                          • Permissions – Roles for RM and permission sets

                              ...

                                • RM IT/Permissions WG


                              December 2020

                              • Data – Courses Data Analysis/Mapping
                                • RA IT/Data WG
                              • Data – Requests Loaded
                                • Data WG/LSIS
                              • Permissions – RM staff assigned permissions
                                • RM IT/Permissions WG
                              • Workflows – all new workflows documented

                                   

                                   

                                    • All ITs/Workflow WG



                                  January 2021

                                  • Decision Checkpoint #1
                                  • Integrations - MM integrations complete
                                  • Ingegrations - CaiaSoft
                                  • Integrations - RM integrations complete
                                  • Data - All data loaded into FOLIO-test
                                  • Gap Analysis – Requirements in Duke Jira vs. Iris

                                   


                                  February 2021

                                  • RA integrations complete
                                  • Reporting – Custom tables creation completed

                                   

                                  ...

                                  • RA Circulation Rules 50% complete
                                    • RA IT/Configuration WG



                                  March 2021

                                  • Permission sets for all roles
                                  • Reporting – Generate reports resulting from gap analysis completed
                                  • Reporting – Deployment of required FOLIO queries on ARC replacment

                                  ...


                                  April 2021

                                  • Decision Checkpoint #2
                                  • Testing scenarios written in Xray
                                  • Gap Analysis – Requirements in Duke Jira vs. Juniper

                                  ...

                                  • RA Circulation Rules complete
                                    • RA IT/Configuration WG


                                  May 2021

                                  • Final testing
                                  • Training materials complete
                                  • Training
                                  • Permissions created for all staff

                                   


                                  June 2021

                                  • Training

                                   


                                  July 2021

                                  • Final training
                                  • Go Live!

                                   


                                  August 2021

                                  • Bug Fixing
                                  • Reporting – Deploy ARC Replacement
                                  • Project Review

                                  ...


                                  September 2021

                                  • Sustainability Plan
                                  • Bug Fixing