Project Board | |
---|---|
Start Date | Sprint zero |
Current Sprint | Sprint #6 22 Apr #8 - 03 |
Target Date | - data freeze / Ex-Libris-imposed-deadline for integrations - Alma Go Live |
Status | See list below for status updates |
Dependencies | Delivery of Duke’s Alma instance (1/18/2024) |
Notes | Target date is set by Ex Libris as part of our project plan. |
...
Priority # | Title | Jira Epic | Importance | Notes | Status |
---|---|---|---|---|---|
1 | Must have before go live |
| File retrievals are running as expected. We have run a full patron synchronization (70,000 records) and it took less than ten minutes, which is awesome. Functionality to include name suffix is done. Incremental can add/update; drop has been developed but not yet tested. EN | ||
2 | Must have at go live |
|
JB | ||
3 | Must have at go live |
Testing uncovered inconsistency in how currency exchange rates are handled. Determined that the Alma export is providing the rate at run time rather than the rate from the date of the invoice. Need to change our invoice total calculation based on this info (and suggested that ExLibris offer this info in their ERP export documentation). Will run a fresh load of test data to send to Duke AP for validation after this change is implemented. | JB 17 Began user training with Law, Ford, and DUL users this week. Identified unexpected behavior with the prorata checkbox and publishing of invoice lines - if special charges such as shipping are listed as invoice lines AND the prorata checkbox on the invoice summary is turned on, those lines will not be included in the export to AP. Will handle through user training and a new error condition. Provided another set of test files to Duke AP for review JB | ||
4 | Must have at go live | Can use code from Harvard as a start | Development is underway.
JB 17 Making progress! Unit testing of invoice creating is underway - the app is sucessfully generating an invoice with lines. Need to change the invoice date value from current date to the invoice date provided in the vendor file. JB | ||
5 | Must have at go live |
| Work is ongoing on viewing item lists and placing requests. We’ve made significant progress in handling various display use cases (claim returned, transit, etc.) Working on an approach to handling records with large numbers of items to address performance. Integration with AEON (for SCL/ARCH holdings) is complete, and integration with ILLiad (for ILR and scan and deliver) is complete. A volunteer external to the library is almost complete in rigorous testing of the CRS with major patron groups and reporting results for adjustments. EN | ||
6 | Must have at go live |
| Configuration in Alma is complete. Data has been extracted from Alma and sent to CaiaSoft. CaiaSoft is actively loading the data to our CaiaSoft test instance. | ||
7 | Must have at go live | Discovery Working Group taking responsibility | Ongoing. Tom C. provided an update at May First Wednesday ( First Wednesday 2024) | ||
8 | Must have at go live |
| Work has begun with Jack Hill and David Chandek-Stark. EN | ||
9 | Must have at go live | or at least by early August | |||
10 | Must have at go live | tied to TRLN Discovery project | Work has begun as part of TRLN Discovery work. EN | ||
11 | Must have by June 10 for ExLibris to load during cutover | Waiting for developer capacity. Open tasks are to fix some bugs and add a few changes based on users feedback to the test data load from December. JB 15 | |||
12 | Post go live | Users will be able to view these logs in Aleph after go-live, but we need to import the data so that’s is available in Alma. | |||
13 | Post go live | Would need to adjust the landing page if not at go live | |||
14 | Migrate FOLIO ERM Organizations Contacts and Interfaces to Alma | Post go live | |||
15 | Post go live | Connection to DSC for item history | |||
16 | Migrate 360 Notes to Alma E-Resources | not yet created | Post go live | The notes in 360 contain information to identify the owning library (Law, Med, etc). |
...