Priority #

Title

Jira Epic

Importance

Notes

Status

1

Patron Loader

AI-31: Patron Loader

Must have before go live

 

File retrievals are running as expected. We have run a full patron synchronization (70,000 records) and it took less than ten minutes, which is awesome. Functionality to include name suffix is done.

Handling dropped patrons is complete. We have one more Jira to complete. We will be good to go-live with the current implementation EN

2

TRLN Discovery/POD/Summon Integration

AI-28: TRLN Discovery/POD/Summon Integration

Must have at go live

 

Testing continues Loading data to confirm that the publishing profile now successfully includes holdings information needed for bound-with recordsthe TRLN SOLR index is underway.

JB 12

3

Invoice Export to Accounts Payable

AI-40: Invoice Export to Accounts Payable

Must have at go live

 

Minimum viable product is complete for go-live. Continuing work on iterative enhancements.

  • Added proper handling of discount lines

  • Adding error handling for funds or vendors with blank external ID values.

  • Additional work needed to operationalize for automatic processing - currently setup to run manually on request in coordination with LSIS so we can ease in and make sure everything is working as expected before fully automating.

JB 13 Finalizing file names and destination server for sending files to AP in production.

JB

4

Invoice Creation from Vendor MARC records

AI-41: Invoice Creation from Vendor MARC Records

Must have at go live

Can use code from Harvard as a start

Analyzed mapping of final price information with MADS. Testing looks good.

Additional jira is in the pipeline to set this up Designing solution for users to run on demand by selecting a file to ingest.

JB 13

5

Catalog Request System

AI-43: Catalog Request System

Must have at go live

 

We’ve completed an implementation of a “read-only” mode that will be used to support the fulfillment freeze and be able to handle any Alma downtimes in the future.

We have remaining jiras, but will be acceptable to go live with what is currently implemented.

EN

6

CaiaSoft

 https://duldev.atlassian.net/browse/AI-118

Must have at go live

 

Configuration in Alma is complete. Data has been extracted from Alma and sent to CaiaSoft. CaiaSoft is actively loading the data to our CaiaSoft test instance.

We’ve begun testing patron requests.
KHN

7

A-Z Journals List

AI-46: Online Journals List

Must have at go live

Discovery Working Group taking responsibility

Ongoing. Tom C. provided an update at May First Wednesday ( First Wednesday 2024)

Library staff have been invited to test the interface and provide suggestions and feedback.

EN

8

Migrate Open Patron Requests from Aleph to Alma

 https://duldev.atlassian.net/browse/AI-34

Must have at go live

 

Successful test run on June 6th; we are prepared for migrating the final data set during fulfillment cutover. This is complete.

EN

9

Bursar Export

https://duldev.atlassian.net/browse/AI-44

Must have at go live

or at least by early August

We’ve begun conversations with the bursar about transitioning to the Alma service output in XML and moving mapping into the data transfer warehouse.

EN

10

Location Guide

 https://duldev.atlassian.net/browse/AI-37

Must have at go live

tied to TRLN Discovery project

Work has begun as part of TRLN Discovery work. EN

11

Migrate FOLIO Licenses to Alma

https://duldev.atlassian.net/browse/AI-35

Must have by June 10 for ExLibris to load during cutover

Complete. Files delivered to ExLibris on 6/10/24

JB

12

Migrate Aleph Order/Subscription Log Notes to Alma Orders

https://duldev.atlassian.net/browse/AI-33

Post go live

Users will be able to view these logs in Aleph after go-live, but we need to import the data so that’s is available in Alma.

13

New Book Carousel

https://duldev.atlassian.net/browse/AI-32

Post go live

Would need to adjust the landing page if not at go live

As long as the catalog date is in the 946B, this will continue to work without development needed.

Metadata Management needs to determine how to include the proper date in the 946B. - EN

14

Migrate FOLIO ERM Organizations Contacts and Interfaces to Alma

https://duldev.atlassian.net/browse/AI-36

Post go live

FOLIO data was archived to a spreadsheet on 6/27/24 so it will be available to load to Alma post-go live. Development work is not yet underway.

15

Alma Cloud App POC for Viewing Item History

https://duldev.atlassian.net/browse/AI-45

Post go live

Connection to DSC for item history

16

Migrate 360 Notes to Alma E-Resources

not yet created

Post go live

The notes in 360 contain information to identify the owning library (Law, Med, etc).

...